Home  |  In the News  |  Project Information  |  Construction  |  Maps  |  FAQ  |  Contact Us


About Cross County
  System Description
Arts in Transit
Related Sites
Search Our Site


General Project Information

The Cross County extension of the MetroLink system will connect additional communities by adding 8 miles to the existing rail system, which currently spans 38 miles from Scott Air Force Base and Shiloh, Illinois to Lambert-St. Louis International Airport.

Cross County includes a major reconstruction of the Forest Park-DeBaliviere station and the addition of nine new stations (two with Park-Ride lots): Skinker, University City-Big Bend, Forsyth, Clayton, Richmond Heights, Brentwood I-64, Maplewood - Manchester, Sunnen, and Shrewsbury - Lansdowne I-44.

Approximately 22 new light rail vehicles will be needed to carry the additional 18,000 daily riders. Construction began in 2003, with revenue service starting in 2006.

By the numbers in 2006

Total Alignment Miles

46

Number of Stations

37

Park-Ride Lots

19

Parking Spaces

10,000

Light Rail Vehicles

87

 

Project Schedule
Preliminary Engineering began May 2000
Final Design began December 2001
Construction began April 2003
Open for Service 2006